Time Summary After Lot Reservation |
|
-
2-7 Days
Client construction financing loan approval.
-
30 Days
Client meets Builder to submit blueprints & complete detail sheet.
-
2 Weeks
Builder returns bid & plan specifications to client.
-
1-2 Days
Client submits blueprints & all forms to Bank.
-
30-45 Days
Bank processes info & prepares loan docs.
-
10-14 Days
Builder applies for permit.
-
4-6 Months
Builder constructs home.
-
MOVE-IN DAY IS HERE!
|